Integrating multiple Any-Cell ESS-L units with an Any-Grid system involves several key steps to ensure optimal performance. Here's how to connect your units: 1. CANbus Communication: For parallel connections to an Any-Grid, establish CAN1 communication across all Any-Cell units. Also, connect CAN2 across all batteries, linking them to the Any-Bridge. Specifically, set CAN1 DIP switch #2 to ON only on the first and last Any-Cell units. For CAN2, set DIP switch #2 to ON only on the last Any-Cell unit. 2. CANbus Termination: Proper CANbus termination is critical. The last Any-Cell in your setup must have CAN2 DIP switch #2 set to ON. If you're using more than one Any-Cell, ensure that the first and last units in the CAN1 chain have their CAN1 DIP switch #2 set to ON. 3. Battery Terminal Connections: When connecting multiple Any-Cells in parallel, use appropriately sized conductors. Route the current path through these conductors to handle the combined current. Make sure to connect the positive and negative terminals at opposite ends of the parallel chain and use equal-length wires for consistent performance. 4. General Setup: After completing the physical connections and wiring, power on the Battery Management System (BMS) of each Any-Cell unit. Verify communication between the Any-Cells, the Any-Bridge, and the Any-Grid to confirm correct operation and data exchange. Following these steps will enable efficient energy storage and usage when integrating multiple Any-Cell ESS-L units with your Any-Grid system.