How to Solve the Charging Pile Issue When Buying a New Energy Vehicle?
1 Answers
The charging pile manufacturer submits the installation materials to the power supply company, requiring the user's ID card copy and the new energy passenger car charging condition confirmation letter. After the manufacturer finalizes the construction plan, the installation and construction phase begins. The construction time varies depending on the conditions of each residential area and the location of the garage. Upon completion of the construction, the charging pile company will report to the power company for on-site inspection and acceptance. If the inspection is passed, the meter will be sealed, and the power company will produce the corresponding power card, which will then be collected by the charging pile company and handed over to the owner.