Oak Run Solar Project: Ohio Power Siting Board to Decide After 2-Year Wait

OKer_x625sgn
08/17/2026, 05:10:14 AM
Oak Run Solar

The Ohio Power Siting Board (OPSB) is now poised to issue a final decision on the Oak Run Solar Project, the largest solar and energy storage facility ever proposed in the state. After a narrow legal remand from the Ohio Supreme Court, the board must determine whether the 800-megawatt solar array and 300-megawatt battery storage system can proceed in Madison County, a region that has fiercely opposed the development.

The clock is ticking for developer Savion. With more than $13 million already invested and a contractual 2030 commercial operation deadline looming, Oak Run’s future hangs on a vote that could come any day now. The OPSB staff recommended approval on Aug. 7, arguing that the developer’s supplemental visual simulations adequately address the only issue the state Supreme Court found insufficient: how the project’s substations would look from public viewpoints.

Court-mandated hearing and the narrow scope of review

The Ohio Supreme Court returned the case to the OPSB in May 2025, instructing regulators to “more thoroughly address the Oak Run project’s visual impacts.” The court had rejected all other objections raised by Madison County and three townships, including concerns about water, wildlife, and battery safety. Only the visual evidence of the three substations was deemed insufficient.

On July 28, administrative law judges held a hearing focusing exclusively on that issue. The developer’s consultant, EDR, produced new photo simulations showing the substations from selected public vantage points. Gordon Perkins, an EDR division manager, testified that the substations “would not contribute to visual impacts that were not already identified” in earlier reviews. The OPSB’s technical staff concurred, and the Aug. 7 staff brief urged the full board to confirm Oak Run’s permit.

But opponents, led by longtime renewable-energy critic Jack Van Kley, argued that the developer’s choice of vantage points was inadequate and that the supplemental materials should have been submitted as part of a formal application amendment, complete with public participation steps. Administrative Law Judges David Hicks and Isabel Marcelletti rejected that argument, siding with the developer and the board’s staff.

A divided court and a growing partisan rift

The Ohio Supreme Court’s May ruling exposed a fractured bench. Six of the seven justices found fault with the OPSB’s original permit approval, but for different reasons. Three said the visual evidence gap was the only problem; three others would have required more evidence on water, wildlife, and battery safety. The sole Democrat, Jennifer Brunner, would have upheld the permit entirely.

That split “added more confusion to an already uncertain legal environment” for large-scale renewables, said Karin Nordstrom, an attorney with the Ohio Environmental Council, which supports the project. “Ohio is facing a massive energy crunch and ever-rising energy prices,” she added. “We really need a clear substantive standard for reviewing these proposed projects, and that’s not what we got from the court.”

The case highlights a broader trend: Ohio has become one of the most hostile states for clean energy development. Since 2021, the General Assembly has enacted laws that create extra hurdles for solar and wind projects while exempting fossil fuel facilities. The OPSB itself has denied permits for other solar projects, including the 94-MW Crossroads Solar Grazing Center and the 175-MW Kingwood Solar installation, which remains in legal limbo after its interconnection agreement expired.

Why Oak Run matters for Ohio’s energy future

Oak Run is not just another solar farm. It would deliver 800 MW of solar power and 300 MW of battery storage — enough to power hundreds of thousands of homes. The project would also generate an estimated $250 million in local tax revenue and create hundreds of construction and permanent jobs.

At the same time, Ohio’s electricity demand is surging, driven by data centers, manufacturing reshoring, and electrification. The PJM Interconnection, which operates the regional grid, has warned that delays in adding new generation could threaten reliability and drive up prices. A 2024 PJM capacity auction showed prices climbing sharply, and the grid operator has flagged the need for thousands of megawatts of new resources by 2030.

“The project represents a significant opportunity for long-term economic investment in Madison County while supporting Ohio’s growing energy needs,” said Samantha Sawmiller, Savion’s senior development manager, in a statement to Canary Media.

Yet the long legal battle has taken a toll. Savion faces contractual deadlines from PJM, equipment suppliers, and financiers. If the project fails to reach commercial operation by 2030 — a deadline that now seems tight — the entire investment could be lost. The developer’s May 18 court filing made the urgency clear: “Oak Run is now in dire need to have the appeals process come to a close as soon as possible.”

What comes next

The OPSB has no statutory deadline to issue its decision. Once the full board reviews the hearing transcript, the staff recommendation, and the briefs, it will vote. Any party could then appeal the board’s decision to the Ohio Supreme Court, further delaying the project.

The outcome could set a precedent for how Ohio handles large-scale renewable projects. If the board approves Oak Run, it may signal that the state is willing to accept clean energy when developers meet strict legal standards. If it denies the permit, the message will be clear: Ohio remains a graveyard for wind and solar.

Given the state’s energy needs and the political landscape, Oak Run is more than a local project — it’s a test case for whether Ohio can balance its growing electricity demand with its desire to regulate renewable development. The next few weeks will determine not only the fate of Oak Run, but also the future of clean energy in the Buckeye State.