September 29, 2026
Eversource and Dartmouth Engineering have been selected for a U.S. Department of Energy award program aimed at expanding the capacity of the existing electric grid across New England. The DOE's Speed to Power (SPARK) initiative could bring approximately $47.7 million to deploy dynamic line rating technology across about 4,000 miles of transmission lines in Connecticut, Massachusetts, and New Hampshire — a project designed to improve reliability and keep customer costs as low as possible.
The selection is a step toward a final award agreement rather than a completed grant. Pending successful negotiations, the project is expected to begin in 2027. The initiative, formally named the Dynamic Rating Enhancement Advancements and Modernization (DREAM) project, is one of 31 selected across 26 states under SPARK, which is run by the DOE's Office of Electricity.
At the center of the project is dynamic line rating, a technology that lets grid operators determine a transmission line's real-time capacity based on current weather and operating conditions, rather than relying on static ratings that assume conservative worst-case scenarios. Because static ratings are usually set below what a line can physically carry, DLR can reveal significant untapped capacity on infrastructure that is already built and energized.
The DREAM deployment will be substantial. Eversource and Dartmouth plan to equip about 4,000 miles of Eversource's transmission network across the three states with DLR systems. The project combines thermal field sensing, which collects on-the-ground measurements of line temperature and physical conditions, with advanced weather forecasting, digital analytical models, and integration tools that present the information to remote system operators in a usable format. The result is a real-time data layer that reflects actual operating conditions, helping operators maximize what the existing grid can deliver.
Eversource transmission president Bill Quinlan said the DOE investment arrives as electricity demand continues to climb across New England. In response to the selection, Quinlan highlighted the project's focus on extracting more capability from the existing transmission system while keeping customer costs down. He called the initiative a demonstration of how advanced grid technology can help meet the region's evolving needs.
Junbo Zhao, associate professor of engineering at Dartmouth and lead researcher on the project, framed the effort around a key challenge in grid operations: existing transmission lines are often capable of carrying more electricity than their standard ratings suggest, but operators lack reliable information about when that extra capacity exists and how to use it safely. Zhao said DREAM's combination of sensing, forecasting, and digital twin analytics transforms that potential into practical tools.
Douglas Van Citters, dean of Dartmouth's Thayer School of Engineering, pointed to the regional pressures that make the project valuable. New England's geography, climate, and growing energy demand make reliable power delivery especially challenging, he said, and linking Dartmouth's modeling expertise with Eversource's operational experience can improve energy security across the region. He described the partnership as an example of research moving from the lab to real-world deployment.
The economic case for the project is built around avoiding new construction. Building transmission lines is costly and time-consuming, with permitting and siting often stretching over a decade. Grid-enhancing technologies like DLR typically cost a fraction of new infrastructure. Eversource said that under specific conditions, the additional transfer capability unlocked by DREAM could reduce or postpone the need for certain new transmission facilities, while also lowering congestion costs on heavily used corridors.
The project's scale sets it apart. Dynamic line rating has been tested on individual lines and small corridors across the U.S., but applying it across a 4,000-mile transmission network would put the DREAM initiative among the largest DLR deployments in the country. The digital twin component — a virtual replica of the transmission system that can be used for scenario analysis and operator training — is also a significant piece of the effort.
The selection reflects a broader federal push to bring grid-enhancing technologies into mainstream use. FERC Order 2023 required transmission providers to consider GETs in their planning, and DOE has followed up with dedicated funding channels such as SPARK. Federal officials have argued that squeezing more capacity out of existing lines is one of the fastest, most cost-effective ways to meet rising electricity demand, particularly as data center growth, electrification, and clean energy interconnection strain the grid.
For New England, the timing is critical. The region has experienced tight supply margins during severe winter weather, and state clean energy goals are adding renewable generation that needs to move across the system. Transmission congestion already shows up in customer bills. Projects that use existing infrastructure more efficiently are viewed by grid planners as a complement, not a replacement, for the broader transmission buildout the region is pursuing.
Eversource, based in Manchester, New Hampshire, is the state's largest electric utility, serving roughly 549,000 homes and businesses in 206 cities and towns. The company has pursued a range of clean energy initiatives, including a networked geothermal pilot, solar, offshore wind, electric vehicle, and battery storage programs. Dartmouth's Thayer School of Engineering has a record of energy research spanning grid modeling, sensor systems, and analytics, with an emphasis on moving discoveries into practical applications.
The next step is the award negotiation process. Eversource and Dartmouth Engineering will work with the DOE to finalize the agreement and project scope. If completed, the funding would support a project scheduled to begin in 2027. More information on the DOE's SPARK program is available on the agency's website.